Friday, October 8, 2010

Holding Pattern

Should I really blog if there isn't a whole lot to say. We choose Benchmark Modern as our contractor. Mark Haslom will be taking on the project. We are slowly getting the budget fit into the tiny hole called the budget. Wish us luck. More to come hopefully next week with a trip to the bank.

Friday, September 17, 2010

Budget Cuts

It's crunch time and we are trimming the fat, or really the house. We are close and with every cut we get closer to our budget. The trombe wall is out, Zinc Roof out, we cut one of the fireplaces, the glass wall has shrunk. Square footage is down to 2665 from 2975 , not to worry the house is still plenty. Just a few more tweeks and we will be at the budget we have been qualified for from the bank. Cross your fingers for a fall ground breaking.


A few of the latest...

Friday, September 10, 2010

End of the line


Well the Cliff Johnson Excavating has finished the waterline including the hydrant. Lot services will be connected next week after it has passed all the tests. These guys were great. Minimal trees were disturbed and they were great communicators as to the daily progress. They also keep in mind that our parents were still living on the lots that the line went through and kept the mess down.
Mean while all the potential contractors sent in the bids. We are in the process of cutting the fat. Two of the three bids were well over $100,000 more than our budget! Zinc roofs, some appliances, Trombe wall are all in negotiations. We are saddened as we thought the house could have been build to our initial budget. This has been a long learning process. Cuts will be made appropriately and all will work out. Folks... do your homework on start up costs!

Wednesday, September 1, 2010

Abby's new tractor

The waterline project marches towards the pasture.

Monday, August 23, 2010

Waterline

The waterline for the building site has started.



Friday, August 13, 2010

5085 South 2050 East



AHHH the smell of diesel fuel... The trees are gone.


We have an entrance. Anyone wanting to visit us now
can enter through our very rough driveway.
High clearance vehicles only.
Construction documents have arrived and are beautiful.
Plans are our to potential contractors and the City of Holladay.
Things are moving right along.


Monday, August 9, 2010

Child Labor

The new gate is painted

Monday, July 26, 2010

Make way

for a driveway.

Before...
During...
After...
Building a gate to keep the creatures in the pasture is next.
Then tree removal. That should really get the gossip flying in the neighborhood.
Construction documents by the end of next week.

Tuesday, July 6, 2010

July

View of the property looking towards Mount Olympus.


Friday, June 25, 2010

Congratulations It's a...

Subdivision. June 24th 2010, 1570 days after we decided to start this process we finally have the Pearce Subdivision recorded with Salt Lake County. It was a huge battle but finally it is finished. Patience is virtue, I guess. We are now in the process of setting up the waterline excavation and getting ready for construction documents from the Imbue team. With any luck will be building a house this August. The latest rendering, dog and chicken included.